← Glossary of termsThe administrative act issued after the technical inspection of a completed building; the building may be used only once it has one (Building Act, NN 155/25, Art. 94). The building authority carries out the technical inspection within 30 or 15 days of a proper application (Art. 98) and issues the permit within eight days of the inspection (Art. 102). For a less complex building (manje složena zgrada) only the investor is invited to the inspection, and only compliance with the location conditions in the permit and the conceptual design is checked (use, external dimensions, plot shape and position of the building), not the basic requirements (Art. 94, 97). The application is accompanied, among other things, by the supervising engineer's final report, a survey of the as-built state and an energy certificate (Art. 95). The obligation to pay the utility charge also begins with the use permit.