← Glossary of termsConditions from public bodies and network operators that the designer obtains electronically through eDozvola before the building permit application (Building Act, NN 155/25, Art. 47). For a less complex building (manje složena zgrada) these are the connection conditions (electricity, water, drainage, traffic area) and the special conditions of the conservation authority if the building is a cultural asset or in a protected area. The body must set them within 30 days; if it does not respond, they are deemed issued (Art. 48). They are valid for two years, and conditions set before 1 January 2026 may be used until 1 January 2028 at the latest (Art. 142).