← Glossary of termsAn electronic notification to the building authority and the building inspectorate at least five days before works start (Building Act, NN 155/25, Art. 89). The contractor and the supervising engineer are named; for a less complex building (manje složena zgrada) the main design, signed with a qualified electronic signature, is attached. From the day of the notice the investor is deemed to have started building (Art. 79) and the five-year period for finishing a less complex building begins (Art. 80). Anyone who builds before the permit is issued pays a special fee, 4,000 euros for a less complex building (Art. 72).