LynxCraft · Academy
← Glossary of termsThe administrative act that sets the location conditions for a development. Under the Spatial Planning Act (NN 155/25), from 1 January 2026, it is issued only for the developments the law lists (Art. 154), for example phased construction, complex buildings and developments, building involving expropriation, developments on maritime domain and power plants, or when the applicant requests it. For a family house it is not a separate step: the location conditions are set in the building permit. A location permit issued before 1 January 2026 is valid for four years from becoming final (Art. 243). It is not the same as location information.