← Glossary of termsA category from the Building Act (NN 155/25), applied from 1 January 2026: a residential building with at most two flats and a gross building area not exceeding 400 m², and an agricultural building of up to 600 m² GBP (Art. 3, para. 1, point 32). The GBP of an ancillary building is not added to the GBP of the house (Ministry opinion of 31 August 2026). For it, the building permit is issued on the basis of a conceptual design (Art. 62), the main design is prepared after the permit and attached to the notice of commencement (Art. 89), a detailed design and BIM are not mandatory (Art. 39, Art. 30), professional supervision covers only mechanical resistance and stability (Art. 26), and the technical inspection checks only the location conditions (Art. 97). It must be finished on the outside within five years of the notice of commencement (Art. 80). Houses of the same size with a permit under the earlier law are also treated as less complex buildings (Art. 137). Most family houses fall into this category.